Project

Balancing of Synchronous Condenser Rotor

Precision Balancing for Synchronous Condenser Rotor at Wind Farm
Service Included:
Vibration Assessment and Measurement

AJSS performed detailed vibration measurements using vibration probes and an optical tachometer to assess the rotor's performance before and after balancing.

Balancing Solution Calculation

Based on readings and customer specifications, AJSS calculated the optimal balancing solution and installed balance weights at the correct locations.

Collaborative Procedure Development

AJSS worked closely with customer engineers to develop the procedure for balancing, ensuring the solution met the customer’s requirements.

Heat Soak and Final Testing

After the balancing weights were installed, AJSS conducted a full heat soak with the rotor connected to the electricity grid to take final readings and ensure the system's stability.

Grid Synchronisation

AJSS ensured that the rotor was correctly synchronised to the electricity grid, confirming its readiness for continuous operation.

Watch Video
No items found.
Location
Regional Victoria, Australia
Timeline
March and May of 2022
Client
Energy technology, solutions and services provider

Brief

  • Customer Industry: Energy technology, solutions, and services provider
  • Project Duration: 2 visits (March and May 2022)
  • Team Involved: 4 AJSS Engineers (Craig Boston, Beau Wignall, Bob Graf, Justin Roth)
  • Vibration Reduction: Non-Drive End Vibration Reduction: 92.5%; Drive End Vibration Reduction: 78.8%
  • Vibration Specification Achieved: Less than 2 mm/sec RMS (Customer's requirement)
  • Readings Taken: Multiple vibration probes and an optical tachometer used for detailed assessment
  • Outcome: Successful synchronisation of the rotor to the electricity grid after balancing

Situation

AJSS was contracted to balance a Synchronous Condenser Rotor located at a wind farm in regional Victoria. The project was completed in two visits by our Field Service and Project Engineers in March and May of 2022.

Task

The Synchronous Condenser Rotor needed to be balanced to the vibrational requirements of the customer. It also needed to be synchronised to the grid. The balancing of the Rotor is vital to ensuring its continuous operation and synchronisation to the electricity grid.

Action

Balance weights that were previously installed by the customer were removed to enable baseline readings to be taken. An optical tachometer and multiple vibration probes were mounted to the Synchronous Condenser Rotor to take readings. AJSS consulted with Customer Engineers to confirm a procedure for balancing the Rotor. Using this procedure a balance solution was calculated, and balancing weights were attached to the specified locations. After a full heat soak with the Synchronous Condenser Rotor connected to the electricity grid, final readings were taken that confirmed the Rotor’s operation matched the calculated solution.

Result

The project achieved its intended outcomes. Our team achieved a 92.5% and 78.8% reduction in vibration on the Non-Drive End and Drive End respectively. As a result, the Synchronous Condenser Rotor was balanced to within the customer’s vibration specification of less than 2 mm/sec RMS. Following this procedure, the Synchronous Condenser Rotor was synchronised to the electricity grid.

Personnel

Lead
Technical Director

Robert Graf

Robert holds a BSc in Mechanical Engineering from the Stevens Institute of Technology and a MBA in Administration (International Finance) from the University of San Diego. He started his professional career in 1977 as a Development Test Engineer for Pratt and Whitney Aircraft in East Hartford, CT, working on FAA flight engine certification programs for the JT8D-209 and JT9D commercial jet engines and in 1980 joined Solar Turbines in San Diego, holding a variety of technical positions culminating the role of Principal Regional Field Engineer for Asia Pacific, based in Singapore. Robert was responsible for the field technical support of complete industrial gas turbine driven generator and compressor packages, and Balance of Plant, used in the oil and gas and power generation industries. Robert’s technical specialties include programming of Logic Controllers, rotor vibration analysis, gas turbine package systems and controls, and gas turbine aerodynamic performance testing. He developed and executed equipment upgrade and retrofit controls products, creating the process control designs, performing the programming tasks, then installing and commissioning these products in the field. Robert also managed a group of 10 Field Service Representatives who were responsible for commissioning and repair of the gas turbine packages. Robert retired from Solar Turbines in March 2018 and joins the AJSS team based out of Singapore. In 2020 Robert was appointed Technical Director.

Connect with Specialists