Project

Compressor Facility Expansion

Powering Up Compressor Facility with Seamless Expansion and Commissioning
Service Included:
Compressor Installation

AJSS managed the installation of new compressor packages (screw and reciprocating compressors) as part of the facility’s expansion.

Mechanical Balance of Plant (BoP) Construction

Ensuring all mechanical aspects of the system are integrated into the existing facility to enhance its capacity.

Commissioning

AJSS assisted in the commissioning of newly installed compressor units, including the integration into the existing system.

Operations Handover

AJSS ensured that the newly integrated compressor units were fully functional and handed over to the client with all operational procedures in place.

Watch Video
No items found.
Location
Queensland, Australia
Timeline
October 2021 to February 2023
Client
Asset Management Company

Brief

  • Project Duration: October 2021 to February 2023
  • Key Personnel: 1 Project Engineer
  • Compressor Packages Installed: 2 new compressor trains (screw and reciprocating)
  • Objective: Increased facility capacity for enhanced operational performance

Situation

AJSS were contacted by a customer to assist with a compressor facility expansion project. The customer was seeking to increase the facility’s capacity through the addition of two new compressor trains consisting of screw compressor and reciprocating compressor packages.

Task

AJSS supplied a Project Engineer responsible for the Compressor packages and the Mechanical BoP work. The Project Engineer worked with the compressor vendor during the fabrication of the compressor packages and factory acceptance testing. The compressor packages were then shipped to Australia for installation and commissioning on site.

Action

The AJSS Project Engineer worked with the Construction team to ensure that the compressor package, including the enclosure, was installed as per the design and OEM requirements. The AJSS Project Engineer developed the scopes of work for conducting the integration of the new compressor packages into the existing facility ensuring there was minimal downtime. Finally the AJSS Project Engineer assisted with the commissioning of the newly installed compressor units and the overall facility for the increased capacity operation. The AJSS Project Engineer then integrated all the new compressor and mechanical assets into the existing operational strategies, plans, schedules, registers, procedures, and work instructions.

Result

AJSS assisted its customer in achieving its goal of increasing its compressor facility expansion resulting in an increased capacity.